Queens Road Bootle

DSCF0115

Beech Group completed Demolition and site clearance of over 300 properties including terraced houses, shops and multi storey dwellings and a school. These works included:

Asbestos Removal.

Soft strip.

Demolition and site clearance (some were separated and demolished by hand due to existing occupants in adjacent houses).

Facade retention provided for various properties to prevent collapse onto the road in front.

The site finish comprised of a reduced dig, 200mm below the slab level and was back-filled with crush.

Knee rail erected around the perimeter of site.

Beech provided scaffolding and associated permits. We also arranged for waste removal and skips to site. We controlled noise and dust so it was kept to a minimum and liaised with surrounding residents to keep a good rapport. We arranged all service isolations including meter removals. A detailed Site Waste Management plan and Health and Safety file was maintained throughout the project. The machines used for this project: PC220 Komatsu with rotation grab and demolition bucket, a 14, 20 and 45 tonne machine and a crusher.

Project was completed on time and on budget.

Accreditations Beech Group Accreditations