Going ….going….gone!

IMG-20151211-WA0006

 

 

The Cracker Head (CCU) demolition has got to be one of this year’s most exciting and challenging projects. Our highly skilled team lifted the 500 tonne structure down to the ground, separated it into sections and processed the stainless steel. This had to be carried out with precision and in very controlled conditions, being in close proximity to live plant. Along with the excellent result came praise from our client in Stanlow. The senior manager there wrote:

 

‘a non routine activity, all works including the lift from its support frame to the clearing of the area post demolition have been completed without incident and in my opinion a very professional manner’.

 

 

 

Accreditations Beech Group Accreditations