Project Details
  • Client Mansells / Cheshire & Cheshire West County Council
  • Budget Undisclosed
  • Duration 4 Months
Looking for something similar? Call us on 0151 645 7571
to discuss your project

University of Chester, Overpool

Beech Group have recently completed the final stages of a demolition workscope at the former University of Chester in Overpool, Ellesmere Port. The extent of the work included the soft strip and demolition of buildings (majority being 2 storey), the excavating of all sub structures and foundations to a minimum of depth of 1 metre, the breaking up of all sub base and kerb foundations to hard landscaped areas and the capping off all drainage /manholes.

Subsoil, topsoil, kerbing and fencing were then all laid and erected to complete the site finish to specification. A high percentage recycling rate was required to be achieved and this was closely monitored by Beech for the correct and efficient removal of all materials from site. To date we have met all targets and are due to complete the programme on time and on budget.

Accreditations Beech Group Accreditations